By-pass to the Barcelona-Vizcaya-Valencia gas pipeline
Natural resources
Start
march
2024
End
march
2025
Location
Barcelona-Biscay-Valencia
Scope
By-pass to the Barcelona-Vizcaya-Valencia gas pipeline
Features
Construction of the by-pass to the gas pipeline between Sagunto and Puçol due to the effect of the Partial Plan of the Parc Sagunt II Area
The total length of the completed bypass is 3,018 metres
Construction, assembly of piping, testing and connection to the gas transmission network
Trenching, transport and unloading work; alignment and bending;, hydraulic testing; and communications system, among others
The discovery of archaeological remains from the Roman period during the construction of the works has posed an additional challenge, consequently promoting several adjustments of the pipeline’s route to safeguard any effect to those remains