By-pass to the Barcelona-Vizcaya-Valencia gas pipeline
Natural resources
Start
march
2024
End
march
2025
Location
Barcelona-Biscay-Valencia
Scope
By-pass to the Barcelona-Vizcaya-Valencia gas pipeline
Features
  • Construction of the by-pass to the gas pipeline between Sagunto and Puçol due to the effect of the Partial Plan of the Parc Sagunt II Area
  • The total length of the completed bypass is 3,018 metres
  • Construction, assembly of piping, testing and connection to the gas transmission network
  • Trenching, transport and unloading work; alignment and bending;, hydraulic testing; and communications system, among others
  • The discovery of archaeological remains from the Roman period during the construction of the works has posed an additional challenge, consequently promoting several adjustments of the pipeline’s route to safeguard any effect to those remains